Expedited Permitting for Electric Vehicle Charging Stations

This page provides all of the needed links to forms and checklists necessary to utilize the City’s Expedited Permitting Process for Electric Vehicle Charging Stations (EVCS). This process provides an expedited and streamlined permitting process for qualifying EVCS systems. Once all of the documentation is correctly and fully completed and submitted, a permit will be processed and approved for issuance in a timely manner (usually 1 to 3 business days).

INSTRUCTIONS:

Step 1 Download, review and complete the City of Sonoma EVCS Checklist. Submit all information requested on the checklist.

Step 2 Apply online for a Building Permit Here.

Communications regarding the Building Permit Application will be through the online portal.